Coverage and film thickness for rubberized bitumen coating

How to convert coverage rates into wet and dry film thickness for rubberized bitumen coating, and estimate the litres and drums a project needs.

Written by the Nuroil trade desk, Sharjah

NURCOAT rubberized bitumen coating
On this page · 6 sections
  1. 01From coverage to wet film thickness
  2. 02Choosing a target thickness
  3. 03Why real consumption is higher
  4. 04Worked estimate
  5. 05Checking on site
  6. 06Quantities and your enquiry

Coverage rates on rubberized bitumen coating data sheets are given in square metres per litre per coat, often as a range such as 1 to 4 m²/L. That range hides a large difference in film thickness. This guide shows how to turn coverage into thickness, how to estimate quantities, and why actual consumption is usually higher than the headline figure.

From coverage to wet film thickness

One litre spread over one square metre forms a layer 1 mm (1,000 microns) thick. That gives a simple relationship:

Wet film thickness in microns = 1,000 ÷ coverage in m² per litre.

The dry film is thinner because the water evaporates. As a working estimate, multiply the wet thickness by the volume solids of the product. Data sheets usually give solids by weight; for water-based coatings with a density close to 1.0 the volume figure is similar, but ask the supplier if an accurate dry film figure matters.

Coverage per coat (m²/L)Wet film (microns)Approximate dry film at 40% solids (microns)Litres per 100 m² per coat
11,000400100
250020050
333313333
425010025
52008020

The table is arithmetic, not a product claim. Some manufacturers publish their own coverage-to-thickness tables; one regional data sheet, for example, gives about 4.5 m²/L for a 150-micron dry film with undiluted product. Where a published table exists, use it.

Choosing a target thickness

Coverage should follow from the dry film thickness required by the project, not the other way round. Lighter rates around 4 to 5 m²/L per coat are used for curing and light protection. Foundation dampproofing generally uses heavier rates and multiple coats. Manufacturers' figures for foundation work range from roughly 1 to 4 m²/L per coat depending on the thickness required. Several thin coats reach a given thickness more reliably than one heavy coat, especially on vertical surfaces.

Why real consumption is higher

Data sheet coverage assumes a smooth, sound surface. On site, several factors increase use:

  • Porosity: open blockwork and dry concrete absorb the first coat. One manufacturer notes coverage of 1 to 3 m²/L per coat depending on porosity.
  • Texture: rough or honeycombed concrete has more surface area than its plan dimensions suggest.
  • Primer coats: diluted priming coats are extra to the main coats.
  • Details: corners, pipe penetrations and construction joints usually receive extra material.
  • Waste: material left in pails, spills and overspray if sprayed.

Many estimators add a margin of 10 to 15 percent for waste and losses, and more for rough surfaces. A trial area on site gives the best figure.

Worked estimate

Suppose a retaining wall has 600 m² of buried face. The design calls for one diluted primer coat and two full coats, each applied at 2 m²/L.

  1. Main coats: 600 m² ÷ 2 m²/L = 300 L per coat, so 600 L for two coats.
  2. Primer: if the primer is the coating diluted with about 20 percent water and applied at around 4 m²/L, it needs roughly 150 L of diluted mix, of which about 125 L is coating.
  3. Subtotal about 725 L. Add 10 percent for losses: about 800 L.
  4. In 200-litre drums that is four drums; in 20-litre pails, 40 pails.

The primer dilution and rate here are illustrative. Follow the data sheet of the product you buy.

Checking on site

A wet film comb gauge, pressed into the fresh coat, shows thickness immediately and costs very little. Checking a few points on each wall panel keeps application consistent. Comparing litres used against area covered at the end of each day is a useful second check.

Quantities and your enquiry

When you request a quote, give the area, number of coats and target dry film thickness, or the coverage rate from your specification, and say whether you prefer pails or drums. Ask for the data sheet's coverage table and the batch certificate of analysis. Nuroil can supply rubberized bitumen coating FOB UAE ports or CFR/CIF on request; use request a quote to send quantities.

PRODUCTS IN THIS GUIDE
KEEP READING

More from the Knowledge Centre.

STILL HAVE A QUESTION?

Ask the people who trade it every day.

Our trade managers answer technical and commercial questions about grades, specifications, packing and shipping.

LET’S TALK ABOUT YOUR REQUIREMENTS

Your next shipment starts here.

Request a quote