Buying furnace oil well is mostly about being precise. A clear enquiry gets comparable offers, reduces disputes at delivery and protects the burner and boiler from fuel they were not designed for. This checklist sets out the points that plant engineers and procurement teams should settle before placing an order.
1. Define the fuel you actually need
- Standard and grade. Name the specification and edition you buy against, such as IS 1593 MV2 or a residual grade under ASTM D396 or BS 2869.
- Viscosity band. Give the range your burner and heaters are set up for, with the test temperature.
- Sulphur limit. Use the lower of the specification maximum and the limit in your emission permit.
- Flash point. Confirm the minimum required for your storage classification; 66 °C is common for residual fuels.
- Pour point. Relevant if tanks or lines are exposed to cool nights or winter conditions.
- Water, sediment and ash. Set maximums that suit your filtration and burner type.
- Extra parameters. Some users also specify vanadium, sodium or calorific value; include them only if they matter to your plant.
2. Describe your site and consumption
- Equipment served: boiler, thermic fluid heater, kiln, furnace or engine.
- Monthly consumption and the size of each delivery your tanks can accept.
- Tank heating available and the temperature at which you receive fuel.
- Access for road tankers: hose connections, unloading pump, weighbridge.
Matching delivery size to consumption keeps stock turning over and reduces ageing and sludge in the tank.
3. Choose delivery mode and terms
| Delivery mode | Typical use | Points to check |
|---|---|---|
| Bulk vessel parcel | Large consumers and distributors with terminal storage | Discharge port, shore tank heating, quantity tolerance |
| ISO tank container | Medium volumes to inland or remote sites | Heating coils in the tank, steam or electric heating at receipt |
| Flexitank | Smaller export lots in standard containers | Suitability for heated cargo and discharge method |
| Drums | Small users, trials, remote locations | Drum condition, heating before decanting, handling equipment |
Agree the Incoterm (FOB, CFR or CIF), the quantity tolerance, how quantity will be determined (shore tank, ship figures or weighbridge) and who appoints the inspector.
4. Agree quality control and documents
- Certificate of analysis for each lot, showing results against your agreed limits.
- Safety data sheet for the product as supplied.
- Certificate of origin if your customs or contract requires it.
- Independent inspection of quantity and quality at loading, if the order size justifies it.
- Retained samples: agree how many are drawn, sealed and kept, and for how long.
5. Prepare to receive the fuel
- Check the receiving tank has enough free space and that heating is working.
- Drain water from the tank bottom before delivery.
- Decide whether the new fuel will be mixed with existing stock and, if so, consider a compatibility check.
- Draw a representative sample during discharge and seal it with the driver or surveyor present.
- Record delivered quantity and temperature so that volume can be corrected to the reference temperature.
Most disputes over fuel oil come down to unclear specifications, unagreed sampling and missing retained samples. All three are settled before the order, not after.
6. Review after each delivery
Note burner behaviour, filter cleaning frequency and smoke readings for the first days on a new lot. Comparing these with the certificate builds a picture of which parameters matter most for your plant and sharpens the next enquiry.
Sending your enquiry
Once these points are settled, the enquiry is short: grade and standard, key limits, quantity per delivery, packing or delivery mode, destination and Incoterm. Nuroil supplies furnace oil worldwide from the UAE on FOB, CFR or CIF terms, with a CoA on every delivery and inspection on request. Send the details through the quote form or contact us.